tq for your info.sy nak check gan rhb nanti. biler tah nak dpt kunci?? project slow.harga rumah emillia pun naik ke 520k.. mcm x caya.
mzakik wrote:Just nak share, bulan lepas saya dapat satu notis dr Maybank saying that Fire/Houseowner Insurance (CAR) dah expired coz project delay. Maybank soh buyer Emillia dapatkan copy renew insurance dr LD dan submit kat Maybank coz LD Development tak renew insurance tu lg. Tp bila saya pergi office LD (15/1), dia langsung tak aware tentang benda ni dan baru nak check & macam diorang tak tau pon aper benda yg dikatakan CAR? yg sedap nyer sorang pompuan dr Credit Control tu kata diorang tak dapat lg. Tp bila tny aper yg awak tak dapat lg? awak nak dapat dr mana? dia xleh jawab...malah dia soh balik dan tunggu ajer...Panassss...
Walhal, semasa saya kompom ngan Maybank, dia bg masa sampai Mid of January ajer, klu tak Maybank akan auto renew CAR insurance & automatically the premium cost mesti ditanggung oleh buyer, byright responsible di bawah LD. So saya kata ngan LD, klu Maybank auto renew, boleh ker saya charge back kpd LD? Diaorg terus cuak..Lepas tu terus dia bincang balik ngan bos dia (Madam Chan), dia promise & kata LD akan settlekan by 23/1.
So, siapa lg buyer Emillia yg amek loan ngan Maybank, mb korang pon da dapat notis yg sama dan boleh f/up ngan LD lepas 23/1.
Saya naik bhgn Development lak, tny tentang CAR...pon sama tercengang2 gak. Tny progress Emillia & bila target nak siap, lg la tak tau...dia terus amek no. contact & promise akan update balik, tp sampai hr ni xkol pon. Terus terpikir, macam diorang ni xamek kesah tentang project Emillia...
norazam18- Posts : 10
Join date : 2012-03-23
Re: Emillia (20x70) b.u. 1822 f
Saya loan ngan RHB..tak ada apa2 notice pun...haihhh..
angin gak ngan LD ni..
angin gak ngan LD ni..
hazrul- Posts : 6
Join date : 2012-11-08
Re: Emillia (20x70) b.u. 1822 f
As Salam...Hari Selasa baru ni saya ada call LD..Diorang kata latest by June boleh dapat kunci..Tak tau la betul ke tak..Dah lama tak tgk site progress...Sape2 yg ada info boleh le share...
MKK- Posts : 5
Join date : 2010-08-28
Re: Emillia (20x70) b.u. 1822 f
wassalam mkk..sakit hati setiap kali baca reply post topic ni. mesti ada jer alasan ntah apa2 dari LD. confirm ker bulan 6? tgk delay lagi. apa yg kita boleh buat utk projek ni dipercepatkan? repot kt mahkamah sivil? urrrrghhhh
khairulaktar- Posts : 1
Join date : 2012-04-03
Re: Emillia (20x70) b.u. 1822 f
Saya baru gi site pagi tadi.. Progress rumah yg menghadap bukit - tembok pagar dah siap, tiles pun dah pasang dlm & luar.. Semua rumah dah ada atap, separuh rumah dah siap plaster.. Longkang pun separuh siap.. Dinding semua rumah pun dah ada.. Rangka tingkap separuh ada.. May b boleh kot kunci dpt bln 6 or 7..
norazam18- Posts : 10
Join date : 2012-03-23
Re: Emillia (20x70) b.u. 1822 f
inilah sebabnya nape umah kite x siap2... developer tgh sakit!!!
Bukak website KPKT, update terkini 8/2/2013, LD dlm senarai hitam pemaju yg terlibat ngan projek sakit.
Tp apsal aku gi tgk arituh projek colaris leh cepat siap drpd emilia plak,, padahal???? perghhh makin sakit hati woooo..
[You must be registered and logged in to see this image.]
Bukak website KPKT, update terkini 8/2/2013, LD dlm senarai hitam pemaju yg terlibat ngan projek sakit.
Tp apsal aku gi tgk arituh projek colaris leh cepat siap drpd emilia plak,, padahal???? perghhh makin sakit hati woooo..
[You must be registered and logged in to see this image.]
nzr187- Posts : 6
Join date : 2013-02-21
Re: Emillia (20x70) b.u. 1822 f
Hi All,
I am one of the owner of Emilia. Last Sunday went to LD office to pay the deposit for water and electricity. I was told by them that the house won't be ready by Hari Raya. I am as disappointed as you even i don't celebrate Hari Raya. No confirm date given. But i have seem some progress in the house as compare to my last visit in March. The wall is now painted(looks like a first layer thing) and they now building the gate. Hope this piece of info helps.
And in case you haven't been to the office/site for a while, FYI, they are LAUNCHING EMILIA 2 in coming 1st June 2013. Showroom (the long abandoned one) is ready for viewing by then. selling Price RM600K++.
Keep in touch in case we need to file complaint together later.
Regards,
Janice Tan
Happy owner of Emilia (not so happy now but still a proud owner of Emilia)
I am one of the owner of Emilia. Last Sunday went to LD office to pay the deposit for water and electricity. I was told by them that the house won't be ready by Hari Raya. I am as disappointed as you even i don't celebrate Hari Raya. No confirm date given. But i have seem some progress in the house as compare to my last visit in March. The wall is now painted(looks like a first layer thing) and they now building the gate. Hope this piece of info helps.
And in case you haven't been to the office/site for a while, FYI, they are LAUNCHING EMILIA 2 in coming 1st June 2013. Showroom (the long abandoned one) is ready for viewing by then. selling Price RM600K++.
Keep in touch in case we need to file complaint together later.
Regards,
Janice Tan
Happy owner of Emilia (not so happy now but still a proud owner of Emilia)
JaniceTanSiewLian- Posts : 4
Join date : 2011-03-27
Re: Emillia (20x70) b.u. 1822 f
There are still vacant units of Emilia and the price now shoots up to RM560k. Got this from LD yesterday.
nor- Posts : 3
Join date : 2013-05-23
Location : Shah Alam
Re: Emillia (20x70) b.u. 1822 f
Went to the office to pay my electricity and water deposit...they are saying that this project will be completed in September...definitely after raya . By the way, i managed to grab Emillia 2 broucher and the starting price is RM750k
anwar982- Posts : 2
Join date : 2013-06-28
Re: Emillia (20x70) b.u. 1822 f
just knew that this project will only completed by November 2013..! Im wondering why LD launch Emillia 9D? 9E pun x siap mengikut jadual... kecewa betul! slow & lembab kerja2 yg dibuat!
norazam18- Posts : 10
Join date : 2012-03-23
Re: Emillia (20x70) b.u. 1822 f
called the office this morning, now they say by December only can compete. timing really bad. Now i dunno if i should change school for my son...
JaniceTanSiewLian- Posts : 4
Join date : 2011-03-27
Re: Emillia (20x70) b.u. 1822 f
Hmmm...It's really bad..They keep delayed the project..Can anybody update the physical progress....
MKK- Posts : 5
Join date : 2010-08-28
Re: Emillia (20x70) b.u. 1822 f
Wow, its become December now? Somehow I am not surprised as the work seems to be progressing really slowly between the once-in-awhile that I drop by.
Was there last weekend on Merdeka day and so far it seems that everything is up just pending doors and windows. External roads also not ready yet and main road access into the area is not even started work. I have a feeling that they plan to handover together with the 24x75 units next to ours.
I guess the delay is likely because of the lack of workers due to the ongoing sweep by Immigration and also the Raya break where many would have returned to their home countries.
Quick question, my bank has started charging for full loan instalment payments now although only about 50% of the loan sum has been disbursed. Are any of you guys having the same?
Was there last weekend on Merdeka day and so far it seems that everything is up just pending doors and windows. External roads also not ready yet and main road access into the area is not even started work. I have a feeling that they plan to handover together with the 24x75 units next to ours.
I guess the delay is likely because of the lack of workers due to the ongoing sweep by Immigration and also the Raya break where many would have returned to their home countries.
Quick question, my bank has started charging for full loan instalment payments now although only about 50% of the loan sum has been disbursed. Are any of you guys having the same?
pritam_singh- Posts : 3
Join date : 2013-02-04
Re: Emillia (20x70) b.u. 1822 f
Yup, i buat loan dgn RHB, this october start to pay the full installment. Rakan-rakan yg lain bagaimana? ada yg buat loan dgn RHB? ada cara x utk kita start bayar bila dh dpt kunci?
nzr187- Posts : 6
Join date : 2013-02-21
Re: Emillia (20x70) b.u. 1822 f
My loan with Rhb.. Till todate only disbursed 65%...pay interest.. Installment x start lg.. Pagi tadi gi site, gate belakang dah pasang.. Tinggal tingkap, pintu, singki & toilet x pasang lagi.. Progress memang terSGT SLOW!!
norazam18- Posts : 10
Join date : 2012-03-23
Re: Emillia (20x70) b.u. 1822 f
Myself personally go & see my house (line belakang facing hutan). Frustrated...jz completed install tile for hall & room, tangga & toilet still no progress. I don't think can finish by end of this year. We need to go to LD office together & pressure them. If one person go, they seems like immune & simply update completion target to us. Myself take loan with Maybank, almost 55% paid rightnow.
mzakik- Posts : 5
Join date : 2012-07-12
Re: Emillia (20x70) b.u. 1822 f
Ok, sekarang kita ramai2 gi serbu LD office utk bertanyakan tentang hal rumah kita... siapa2 yg bersetuju kita set date & time..
Cadangan :
Date : 12 Oct 2013 (Saturday) or maybe weekdays
Time : 10 pagi (depan ofis LD)
Cadangan :
Date : 12 Oct 2013 (Saturday) or maybe weekdays
Time : 10 pagi (depan ofis LD)
nzr187- Posts : 6
Join date : 2013-02-21
Re: Emillia (20x70) b.u. 1822 f
Received notice from LD, the internal & external plastering completed and asking bank to pay 10%. Total withdrawer 75%. Actual completion, not sure. Last visit to the house on 5th oct, toilet not done yet. Some houses even the window not installed. Hope we can get it by Dec.
JaniceTanSiewLian- Posts : 4
Join date : 2011-03-27
Phone number.
Salam semua,
Tolong tinggal no. telofon semua kat sini utk senang dihubungi.
Kalau nak buat bantahan kan LD pun senang nak kumpul org. Page ni nampak gayanya jarang2 je kita semua bukak.
mungkin dah malas nak layan kerenah LD ni. I Baru dpt msg from bank yg full installment dah kena bayar start 1 dec 2013. Kunci tak tau cerita lagi...
So, drop your phone no. and we can create whatapps group later.
Thank you
Tolong tinggal no. telofon semua kat sini utk senang dihubungi.
Kalau nak buat bantahan kan LD pun senang nak kumpul org. Page ni nampak gayanya jarang2 je kita semua bukak.
mungkin dah malas nak layan kerenah LD ni. I Baru dpt msg from bank yg full installment dah kena bayar start 1 dec 2013. Kunci tak tau cerita lagi...
So, drop your phone no. and we can create whatapps group later.
Thank you
hazrul- Posts : 6
Join date : 2012-11-08
Re: Emillia (20x70) b.u. 1822 f
Kalau gomen loan, selamat sikit..selagi tak dapat kunci, tak deduct...fizi.suhaimi wrote:Hafizi Suhaimi 0199790044
hayusri- Posts : 33
Join date : 2010-08-03
Group
Create group cepat sikit, dan discuss apa yang perlu buat.
hayusri- Posts : 33
Join date : 2010-08-03
Re: Emillia (20x70) b.u. 1822 f
Ok.. Kalau ada yg respond ok je... My no 012 446 0646... Naya la buat loan swasta ni...
hazrul- Posts : 6
Join date : 2012-11-08
Re: Emillia (20x70) b.u. 1822 f
I just been informed that this project will be delay untill Jan 2014..reason due to short of raw material and blah...blah... tiang lampu dah pacak, ada certain rumah tiles x complete... anak nak tukar sekolah pun kena postponed....
norazam18- Posts : 10
Join date : 2012-03-23